  • SIDA provided 1200 number of Pre-fabricated houses out of which 416 completed and 383 handed over to affectees. 283 under construction.
  • Saudis are Starting Work on 1000 Pre-fab Houses.
  • Work on CMH Muzaffarabad started
  • ICRC Rehab Centre Complete and functional
  • Construction of 53 Houses in Jalalabad. 13 Completed.
  • University Campus Muzaffarabad Functional in Pre-fab Building
  • Makrri and Kahorri Bridges Launched.
  • Blood Transfusion Centre AIMS Functional
  • Micro/Master Plan of Muzaffarabad City approved.
  • 219 people granted NOCs for construction of houses in M,abad City. Consultant on Board.
  • Sites of Satellite Towns identified. Land record under preparation.
  • 56 kanals of Land allocated for Prince Ahmed Central City Mosque
  • Rubble Recycling Plant will Start Work soon.
Muzaffarabad City Development Project Cost USD 347 Million.
Chinese Share
i. Road and Bridges =US$ 106.35 Mil.
ii. Cost of Project Master Plan proposal =US$ 133.699 Mil.
iii. Unallocated for other projects* =US$ 60. 29 Mil.
(Consultancy fee included in the cost of project @ 7% of the estimated project cost)
Total Cost (A) = US$ 300 Million.

* Reserve amount for projects identified in the course of finalization of settlement plans and overall master plan.

GOP Share
i. Roads and Bridges = USD 23 Million
ii. Cost of Project Master Plan Proposal= USD 22.15 Million
iii. Unallocated for other Projects= USD 1.85 Million
Total= USD 47
Rough estimates Exact to be determined by Board of Revenue during land acquisition process and financed from GoP counterpart funds
  • Micro Planning and detailed designing of West Bank Road and Naluchi Bridge completed by the JICA.
  • House reconstruction along Primary/Secondary Roads has been allowed. The Development Authority Muzaffarabad out of which 72 applicants have been given NOC received 84 applications for reconstruction of houses in Muzaffarabad City.
  • Kingdom of Saudi Arabia would build AJK University at Chattar Kalass. PC-1 for 1,000 and 500 kanals of land for Muzaffarabad University Campus and Rawalakot University Campus respectively has been prepared and furnished to ERRA for approval.
  • Construction of CMH Muzaffarabad by UAE, Contractor mobilized, work started.
  • SIDA provided 1200 Pre-fab houses for Muzaffarabad out of which 165 have been completed .
  • AIMS Work initiated.
  • Debris removal work awarded and work started.
PROGRESS ON MCDP IMPLEMENTATION AS OF 24TH SEPTEMBER 2007
  • Work awarded to two Chinese Firms
  • Beixin: Roads & Bridges
  • CWE: Buildings & Other Facilities
  • Both the firms established their offices in Muzaffarabad since 21st August 2007 and started work at full pace.